Southern California Edison's Antelope-Pardee 500-kV Transmission Line Project


Construction Photos
Segment 1, Sections 1 and 3

Demolition of the old 220-kV single-circuit towers in Santa Clarita. Once the old towers are removed, the new double-circuit towers are built in their place.


Construction of a new single-circuit lattice tower using a crane.


Construction of the new 500-kV Antelope-Pardee lattice towers in Lancaster.


Sections of the new lattice towers are lifted by a crane into place.


New single-circuit 500-kV poles along the Antelope-Pardee corridor in Lancaster.


Wire pulling site in Santa Clarita to support the installation of wire into the new double-circuit lattice towers


This page contains tables and is best viewed with Internet Explorer or Mozilla Firefox. Please report any problems to the Energy Division web coordinator.