PACIFIC PIPELINE PROJECT MITIGATION MONITORING,
COMPLIANCE, AND REPORTING PROGRAM
SEPTEMBER 1998 - MONTHLY REPORT

The following constitutes the September 1998 Monthly Report for the Pacific Pipeline Mitigation Monitoring, Compliance, and Reporting Program (MMCRP) contract. It should be noted that since the start of construction daily and weekly reports summarizing monitoring activities have been issued and are available on the project web site for review.

CONSTRUCTION MONITORING

Segment 1 Construction: Segment 1 runs from the southern end of the San Joaquin Valley at Emidio, through the Tejon Pass, to the northern boundary of the ANF in Los Angeles County. Construction of Segment 1 commenced on November 5, 1997. Primary activities during the month of September are presented in Table 1. No non-compliance events occurred on Segment 1 during September.

During September, three separate crews worked on Segment 1. The horizontal directional drill at Cuddy Creek (EMP 25.15 to 25.52) encountered problems with the 32-inch drill when a void under Peace Valley Road collapsed the night of September 4. Crews worked over the Labor Day weekend to enact repairs. The drill became stuck again on September 11. Problems with the drill continued throughout the month of September, slowing progress. Repairs to Peace Valley Road, required as a result of the drill, were overseen by a Los Angeles County inspector.

During September, work continued at Tejon wetland (EMP 20.11 to 20.44) where a section of pipe had to be removed because of poor welds. Work was also conducted on the Wheeler Ridge Road bore (EMP 10.63) and at the block valve north of the California aqueduct (EMP 12.02). Work along Tejon Bench (EMP 15.57 to 20.10) continued throughout the month. Concrete work at Emidio Pump Station (EMP 0.00) was completed and building erection and pump installation was conducted in conjunction with associated electrical work. Grading and foundation forms at Grapevine Pump Station (EMP 15.57) were completed and concrete pouring began. Work on Segment 1 was shut down on September 4 because of heavy rains. With the exception of the Cuddy Creek directional drill crew, no work was conducted on Labor Day, September 7.

Table 1. Construction Activities for Segment 11

Activity

Milepost (approximate)

Pot-hole

1.06 to 5.66, 16.93 to 17.32, 17.72 to 17.64

Clearing

16.99 to 18.48

Trench

2.59 to 7.09, 18.39 to 18.99

Lower-In

3.76 to 7.37, 18.65 to 19.45, 20.24 to 20.43

Coating

3.76 to 7.48, 10.67 to 10.99, 18.65 to 18.93, 19.22 to 19.54

Conduit

2.61 to 7.81, 10.67 to 12.32, 19.23 to 19.69

Backfill

4.47 to 7.81, 10.67 to 12.32, 19.23 to 19.69

Emidio Pump Station - In Progress

0.00

Bore (Wheeler Ridge Road) - In Progress

10.63

Block Valve (North side California Aqueduct) - In Progress

12.02

Bore (I-5 crossing @ Tejon Ranch) - In Progress

13.33

Grapevine Pump Station - In Progress

15.57

Bore (I-5, north of Lebec Road overpass) - Complete

20.79

Bore (Lebec Road, south of overpass) - Complete

21.20

Bore (Lebec Road, Specimen Tree #2) - Complete

24.82

Directional Drill (Peace Valley & Lebec Roads, Cuddy Creek) - In Progress

25.15 to 25.52

Check Valve (Peace Valley Road, Cuddy Creek) - Complete

25.92

Bore (Stream Crossing #20) - Complete

27.43

Bore (Stream Crossing #21) - Complete

27.81

Bore (Stream Crossing #23) - Complete

28.10

Block Valve (Gorman) - Complete

28.33

Directional Drill (Gorman Slide) - Complete

28.68 to 29.68

Block Valve (San Andreas) - Complete

30.43

Bore (Stream Crossing #29) - Complete

32.38

Bore (Stream Crossing #30) - Complete

32.71

Block Valve (Copco Road) - Complete

32.81

1. Construction progress from August 31 through September 27.

Segment 2A/C (ANF) Construction: Construction within the ANF (Segment 2A) began on June 27, 1997 and was completed to Templin Highway on November 9, with the exception of some erosion repair, revegetation, valve, and conduit requirements. This follow-up work commenced in June 1998. Construction of Segment 2C, Templin Highway to Castaic (several miles south of the southern ANF boundary) commenced on June 22, 1998; portions of Segment 2C also traverse private lands. Construction of both Segment 2A and 2C (ANF portions) is required by the ANF to be completed by October 3, 1998. Primary activities during the month of September are presented in Table 2. Table 3 presents the non-compliance events that occurred on Segments 2A or 2C during September.

Table 2. Construction Activities for Segment 2A/C1

Segment

Activity

Milepost (approximate)

Segment 2C

Trench

52.51 to 53.58

  Lower-In

50.82 to 51.25, 51.90 to 52.11

  Coating

50.82 to 50.95, 51.30 to 52.51

  Conduit/Backfill

50.82 to 51.30, 51.98 to 52.51

  Whitaker Pressure Relief Station - In Progress

51.35

  Bore (Under I-5) - Complete

53.48

  Block Valve (Lake Hughes) - Complete

56.53

  Bore (Marple-Violin Canyon Creek) - Complete

56.74

1. Construction progress from August 31 through September 27.

Table 3. Non-Compliance Events for Segment 2A/C (ANF)1

Segment

Mitigation Measure/PC

Description/

Non-Compliance Level

First

Observed

Corrected

Status

2C

SS-2.2: Hand excavate when within 24-inches of marked utilities. Track how hit marked crude oil pipeline - Level 3.

9/18/98

9/18/98

Acceptable

1. Non-compliance reports issued from August 31 through September 27.

Segment 2A - During September, erosion repairs/prevention and reseeding was conducted along skipped areas between EMP 43.14 and 49.42. Erosion repair and reseeding also occurred at several valve sites (EMP 36.02, 37.62, and 44.36). In addition, electrical work was conducted at the valve sites. Installation of the fiber optic cable was also completed. A sizing plate and caliper pig were run through the northern section of Segment 2A. Anomalies were recorded and located. Pipe was excavated at EMP 38.90 to locate the anomalies. Installation of the hydrostatic-test-water-pipeline along School Bus Road was completed in accordance with approved Variance Request #111. No work occurred on September 4 because of heavy rains or on the Labor Day holiday, September 7.

Segment 2C - During September, the contractor had three construction zones with Segment 2C (ANF portions) in order to complete construction on ANF lands before the October 3 deadline. The bore under Interstate 5 (EMP 53.48) was completed. Preparation of the all-weather road that will access Whitaker Station (EMP 51.35) and associated roadway culverts was completed during September. Work commenced at the Whitaker Station including site preparation, construction of retaining walls and vault building, and installation of electrical housings. Work was suspended on September 4 because of heavy rains and no work occurred on the Labor Day holiday, September 7.

Segment 2B (Non-ANF) Construction: Segment 2B runs from Castaic to Sylmar, paralleling I-5. Construction of Segment 2B commenced on November 6, 1997. Primary activities during the month of September are presented in Table 4. No non-compliance events occurred on Segment 2B during September.

During September, most Segment 2B crews were moved to Segment 2C to facilitate completion of construction on ANF lands by October 3, 1998. Equipment was also transported from Segment 2B to Segment 1 to assist in pulling the stuck directional drill pipe at Cuddy Creek. Remaining crews worked on pipe tie-ins at McBean Parkway and Feedmill Road, backfilled and recontoured the Valencia Boulevard bore site, completed seeding and mulching along the Newhall Land and Farming property, installed fiber optic cable across Castaic Creek, and did general right-of-way clean up from Magic Mountain Parkway to Calgrove Boulevard.

Table 4. Construction Activities for Segment 2B1

Activity

Milepost (approximate)

Pot-hole

71.80 to 73.80

Bore (Church Street) - Complete

58.24

Check & Block Valves (South of Church Street) - Complete

59.15

Bore (South of Romero Canyon) - Complete

59.39

Bore (Hillcrest Parkway) - Complete

59.77

Block Valve (Live Oak) - Complete

61.10

Directional Drill (Castaic Creek/Live Oak) - Complete

61.14

Check Valve (South of Live Oak) - Complete

61.56

Bore (South of Highway 126) - Complete

62.78

Check Valve (South of Highway 126) - Complete

63.17

Directional Drill (Santa Clara River) - Complete

63.46

Bore (Feedmill Road) - Complete

63.93

Check Valve (Magic Mtn. Parkway) - Complete

64.01

Bore (PGA Ranch) - Complete

65.38

Bore (PGA Ranch) - Complete

65.52

Bore (PGA Ranch) - Complete

65.62

Block Valve (Pico Canyon Road) - Complete

67.46

Check Valve (Lyons, Old Road) - Complete

68.68

Bore (Calgrove Avenue) - Complete

69.13

Bore (Old Road @ I-5) - Complete

69.99

Block Valve (Sylmar Station) - Complete

73.81

1. Construction progress from August 31 through September 27.

Segment 3 Construction: Segment 3 runs from Sylmar to Dodger Stadium, primarily within MTA right-of-way. Construction within the City of San Fernando, between Wolfskill and Jessie Streets (approximately 190 feet), began on September 30, 1997, and was completed on October 7, 1997. Construction of the remaining portions of Segment 3 commenced on October 28. 1997. On February 5, 1998, a mini-crew began work on Segment 3 in the vicinity of Los Feliz (referred to as "Los Feliz" crew). This crew worked primarily at the StorItAll facility and the Glendale Boulevard bore which were completed during April 1998. In April 1998, Segment 3 construction was divided into two spreads (Segment 3A which runs from San Fernando to south of Taylor Yard, and Segment 3B which runs from Taylor Yard to Alameda Street). A Segment 3C crew (San Fernando north to Sylmar) was added the second week of September, 1998. Primary activities during the month of September are presented in Table 5. Table 6 presents the non-compliance events that occurred on Segment 3 during September. No work occurred on Segment on Labor Day, September 7.

Segment 3A - During September, Segment 3A crews concentrated on completing work between Allen and Grandview Streets and completing the Los Feliz bridge crossing (EMP 93.01). Crews worked three nights to install brackets and hangers for the pipe installation at the Los Feliz bridge crossing, where pipe was successfully installed. The bore at Van Nuys Boulevard (EMP 79.65) commenced in September, but was stalled because of equipment problems. Preparatory work began at the Colorado Street overpass and the skip at Sonora Avenue (EMP 89.97) was completed.

Segment 3B - During September, construction progress along Segment 3B included the pouring of concrete, removal of forms, and final asphalt work within the MTA maintenance facility. Work was also conducted at the bore at EMP 97.10, but was slow because large boulders and I-beams were encountered. The bore was completed by the end of the month.

Segment 3C - During September, Segment 3C crews concentrated on pot-holing and clearing the 3.5 miles of pipeline right-of-way within the MTA rail right-of-way. Trenching began on September 10. The construction yard within San Fernando was reactivated and is being used for spoils storage. Pipe north of Hubbard Street (EMP 76.96) was excavated and removed because pipe with the incorrect wall thickness had been installed.

Table 5. Construction Activities for Segment 31

Segment

Activity

Milepost (approximate)

Wolfskill to Jessie Streets Cased bore - Completed

78.52

  Pipeline/conduit installation - Completed

78.37 to 78.57

Segment 3A

Pot-hole

89.90 to 90.43

  Trench

89.90 to 90.43, 93.01 to 93.15

  Lowering-In

89.56 to 90.43, 93.01 to 93.15

  Coating

89.50 to 90.43, 93.01 to 93.15

  Conduit

89.43 to 90.43, 93.01 to 93.04

  Backfill

89.43 to 90.43, 93.01 to 93.04

  Bore (Maclay Avenue) - Complete

78.02

  Bore (Brand Boulevard) - Complete

78.16

  Bore (Wolfskill Street) - Complete

78.33

  Bore (railroad crossing) - Complete

78.37

  Bore (Paxton Street) - Complete

79.11

  Bore (Van Nuys Blvd) - In Progress

79.65

  Bore (Pierce Avenue) - Complete

79.93

  Bore (Osborne Street) - Complete

80.74

  Bore (box culvert) - Complete

81.19

  Bore (Branford Street) - Complete

81.29

  Block Valve (Tujunga Wash) - Complete

81.48

  Bore (Sheldon Street) - Complete

82.11

  Bore (Penrose Street) - Complete

83.48

  Bore (Sunland Avenue) - Complete

84.09

  Bore (Arvilla Avenue) - Complete

85.02

  Bore (Buena Vista Avenue) - Complete

86.37

  Block Valve (RITC) - Complete

87.43

  Directional Drill (Burbank Crossing) - Complete

87.48 to 88.65

  Block Valve (Allen Avenue) - Complete

89.33

  Bore (Bekins Way) - Complete

90.86

  Block Valve (Verdugo Wash) - Complete

90.95

  Bore (Aviation Avenue) - Complete

91.21

  Bore (Broadway/Brazil) - Complete

91.69

  Bore (Workers Center) - Complete

91.89

  Bore (Riverdale Avenue) - Complete

92.32

  Block Valve (Hollywood Fault) - Complete

93.36

  Check Valve (Hollywood Fault) - Complete

93.59

  Bore (Glendale Boulevard) - Complete

93.76

  Bore (railroad crossing) - Complete

93.79

  Bore (railroad crossing) - Complete

94.56

  Block Valve (Tyburn Street) - Complete

94.71

  Bore (Sycamore Wash) - Complete

94.92

  Bore (UP railroad crossing) - Complete

95.42

  Block Valve (Los Angeles River) - Complete

95.96

Segment 3B

Bore (entry road to MTA) - Complete

96.00

  Bore (railroad crossing) - Complete

96.10

  Bore (railroad crossing) - Complete

97.10

  Bore (railroad crossing) - Complete

97.33

  Bore (railroad crossing) - Complete

97.35

  Block Valve (Cornfield Yard) - Complete

98.48

Segment 3C

Pot-hole

74.48 to 77.18

  Trench

76.40 to 76.97

  Lower-In

76.95 to 77.18

  Coating

76.65 to 77.15

  Conduit

79.96

  Backfill

79.96

  Block Valve - Complete

76.63

Los Feliz

Pipeline Installation - Complete

93.14 to 93.78

  Valves (StorItAll) - Complete

93.48

  Bore (Glendale Blvd.) - Complete

93.78

1. Construction progress from August 31 through September 27.

Table 6. Non-Compliance Events for Segment 31

Segment

Mitigation Measure/PC

Description/

Non-Compliance Level

First

Observed

Corrected

Status

3B

B-AQ-1.8: Abide by Storm Water Pollution Prevention Plan. Drips and spills not cleaned up in area adjacent to Los Angeles River - Level 1.

9/15/98

9/17/98

Acceptable

1. Non-compliance reports issued from August 31 through September 27.

Segment 4 Construction: Segment 4 is being constructed by two separate crews. Construction of Segment 4A, from downtown Los Angeles to Watts Junction, began on October 20, 1997, and is being conducted from 7:30 p.m. to 6:00 a.m., Monday night through Friday night, to minimize traffic impacts. A Segment 4A-day crew was added the end of June through August, 1998. Segment 4B construction (daytime), from Watts Junction to the Chevron El Segundo Refinery, commenced on October 23, 1997. Primary activities during the month of September are presented in Table 7. Table 8 presents the non-compliance events that occurred on Segment 4 during September. Segment 4 crews did not work the Labor Day holiday, September 7.

Segment 4A (nights) - During September, separate crews worked the north and south ends of the segment. The removal of hand-hewn granite blocks continued to be monitored by archaeological specialists and the Native American monitor. An archaeological specialist representing the Lead Agencies inspected construction on September 17, 1998. Pipe casing installation was completed at the Highway 101 overcrossing. Mainline construction activities were completed on the south end of Segment 4A. Work commenced at the College Street crossing, requiring a trench depth of up to 25 feet, and at the 92nd Street bore (EMP 106.45).

Segment 4B - During September, mainline construction occurred near Compton Avenue, Slater Avenue, 108th Street, 109th Street, 110th Street, Central Avenue, Alameda Street, and Fernwood Street. Crews also worked on vault installation at Central Avenue and Lanzit, and installation of fiber optic cable at 110th Street, Central Avenue, and the Interstate 405 overcrossing. Work commenced at the Lynwood Station including site preparation and hand digging of footings. Clean-up of the El Segundo Station site also began.

Table 7. Construction Activities for Segment 41

Segment

Activity

Milepost (approximate)

4A

(nights)

Pot-hole

98.48 to 99.12, 106.15 to 106.39

  Trench

98.48 to 99.12, 106.13 to 106.39

  Lower-In

98.53 to 99.12, 105.84 to 106.45

  Coating

98.55 to 99.12, 105.62 to 106.45

  Conduit

98.60 to 99.28, 105.54 to 106.45

  Backfill

98.60 to 99.28, 105.44 to 106.45

  Block Valve (7th Street) - Complete

100.69

  Bore (railroad crossing) - Complete

102.08

  Block Valve (25th Street) - Complete

102.17

  Bore (Slauson Avenue) - Complete

103.89

  Bore (Randolph Street) - Complete

104.07

  Block Valve (Southgate) - Complete

105.85

  Bore (92nd Street) - In Progress

106.45

4A (days)

Bore (Alameda St. & Fernwood Ave.) - Complete

107.86

  Bore (E. Alameda & Martin Luther King Jr. Blvd) - Complete

108.50

4B

Lynwood Station - In Progress

ESMP 0.00

  Trench

ESMP 0.04,

ESMP 1.190 to ESMP 1.51

  Lower-In

ESMP 1.47 to ESMP 1.68

  Backfill/Conduit

ESMP 1.29 to ESMP 1.76,

ESMP 1.85 to ESMP 1.87,

ESMP 3.05

  Bore (108th Street) - Complete

ESMP 1.10

  Bore (108th Street) - Complete

ESMP 1.15

  Block Valve (Between 109th and 110th Street) - Complete

ESMP 1.22

  Bore (109th Street) - Complete

ESMP 1.25

  Bore (Compton Street) - Complete

ESMP 1.38

  Bore (by LAFCD, east of Slater) - Complete

ESMP 1.56

  Bore (Slater Avenue) - Complete

ESMP 1.68

  Bore (Central Avenue) - Complete

ESMP 1.70

  Check Valve (by Compton Creek) - Complete

ESMP 1.91

  Bore (Avalon Street) - Complete

ESMP 2.52

  Bore (San Pedro & Emperial Hwy #1) - Complete

ESMP 2.74

  Bore (San Pedro & Emperial Hwy #2) - Complete

ESMP 2.79

  Bore (San Pedro & Emperial Hwy #3) - Complete

ESMP 2.81

  Directional Drill (Hoover to Main) - Complete

ESMP 3.04 to 3.84

  Bore (Vermont Avenue) - Complete

ESMP 4.12

  Bore (Budlong Avenue) - Complete

ESMP 4.34

  Bore (Western Avenue) - Complete

ESMP - Complete

  Bore (Van Ness Avenue) - Complete

ESMP 5.90

  Bore (Wilkie Avenue) - Complete

ESMP 6.27

  Block Valve (east of Dominguez Channel) - Complete

ESMP 6.36

  Bore (by Dominques Channel) - Complete

ESMP 6.41

  Bore (Crenshaw Blvd.) - Complete

ESMP 6.46

  Check Valve (east side of Crenshaw) - Complete

ESMP 6.48

  Bore (Prairie Avenue) - Complete

ESMP 7.45

  Bore (York Avenue) - Complete

ESMP 7.51

  Bore (Oxford Avenue) - Complete

ESMP 7.57

  Bore ( Menlo Avenue) - Complete

ESMP 7.64

  Bore (Freeman Ave.) - Complete

ESMP 7.70

  Bore (Cedar Avenue) - Complete

ESMP 7.76

  Bore (Birch Avenue) - Complete

ESMP 7.82

  Bore (Hawthorne Blvd.) - Complete

ESMP 7.99

  Bore (Grevillea Avenue) - Complete

ESMP 8.09

  Bore (Eucalyptus Avenue) - Complete

ESMP 8.34

  Bore (Inglewood Avenue) - Complete

ESMP 8.50

  Directional Drill (El Segundo & I-405) - Complete

ESMP 8.93 to 9.38

  Bore (Aviation Blvd.) - Complete

ESMP 9.60

  Bore (Douglas Blvd) - Complete

ESMP 9.87

  Bore (between Sepulveda & Douglas) - Complete

ESMP 10.44

  Bore (between Sepulveda & Douglas) - Complete

ESMP 10.55

  Bores (Sepulveda & Allied Yard) - In Progress

ESMP 10.78

  El Segundo Station - In Progress

ESMP 10.78

1. Construction progress from August 31 through September 27.

Table 8. Non-Compliance Events for Segment 41

Segment

Mitigation Measure/PC

Description/

Non-Compliance Level

First

Observed

Corrected

Status

4B

SS-2.2: Hand excavate within 24-inches of marked utilities. Excavator hit marked water line - Level 3.

9/11/98

9/11/98

Acceptable

1. Non-compliance reports issued from August 31 through September 27.

Segment 5 Construction: This segment involved 3 phases of operation, construction of Segment 5A (Dominguez Channel to Sepulveda Blvd. - MP 116.21 to 116.75) has been completed. Construction of Segment 5B (along Alameda Street south of Sepulveda Blvd. and south along Henry Ford to Anaheim Street - MP 116.75 to 118.83) was completed during September 1997. Construction of Segment 5C (remainder of Segment 5 - MP 107.95 to 116.21) commenced on August 29, 1997 and was completed in September 1998 with the exception of the directional drill of Auto Drive South which will begin upon the completion of the Cuddy Creek directional drill on Segment 1 and directional drill of the Santa Clara River for fiber optic conduit installation on Segment 2B. Primary activities during the month of September are presented in Table 9. No non-compliance events occurred on Segment 5C during September.

Table 9. Construction Activities for Segment 51

Activity

Milepost (approximate)

Lower-In

113.15 (complete)

Coating

113.15 (complete)

Conduit

113.00 to 113.15 (complete)

Backfill

113.00 to 113.15 (complete)

1. Construction progress from August 31 through September 27.

 

VARIANCES

During September, the following variances were approved/denied:

Table 10. Variance Approvals/Denials

Variance #

Description

Segment(s) Variance Applies

Agency Decision

72

Open cut trenching of Polk Street (instead of boring), City of Los Angeles

3

Approved

110

Sunday work on Segment 2C and 24-hour concrete work at Whitaker Station.

2C

Approved

111

Installation of temporary 8" water line for hydro testing.

1

Approved

112

Install fiber optic cable at Santa Clara River via directional drill.

2B

Approved

115

Revise timing of smart pigging as required by Mitigation Measure SS-49**.

All

Approved

116A

Open cut trenching of College Avenue instead of boring.

4A

Approved

116B

Sunday work on ANF from Copco Road south to Templin Highway.

2A

Approved

CONSTRUCTION YARDS/STAGING AREAS

During September, the following construction yards/staging areas were approved/denied:

Table 11. Construction Yard/Staging Area Approvals/Denials

Request #

Construction Yard/Staging Area

Applicable Segment(s)

Agency Decision

69

Temporary work space for College Street bore pit.

4A

Approved

70

Construction yard and material storage at Cornfield Railyards.

3

Approved

71

Temporary work space for bore pit and spoil storage along Sepulveda Blvd at Chevron metering station.

4B

Approved

72

Extra work space at Balboa Blvd and Balboa Road.

2B

Approved

73

Extra work space along San Fernando Road just south of Balboa Blvd overpass.

2B

Approved

74

Extra work space along San Fernando Road just south of the Antelope Valley Freeway overpass

2B

Approved

 

Compliance Documentation: PPSI’s general plans and reports have been submitted and approved by the CPUC and ANF. Outstanding plan issues relate only to proposed revisions to approved plans (submitted by PPSI as variance requests, documented above) or updated plans. The remaining compliance issues that must be documented prior to or during construction on each segment relate to: (1) obtaining permits or landowner agreements from local jurisdictions and landowners, (2) completion of Traffic Control Plans and their approval by local jurisdictions, and (3) completion of the landowner, resident, and business notification processes. In addition, during September, pre-construction compliance review for the Whitaker Pressure Relief Station was completed (final HAZOP review pending) and a Notice to Proceed for station clearing, grading, and foundation work was issued on September 2.

With pipeline operations projected by PPSI to start by years end, numerous compliance submittals were provided for review and approval by PPSI for pre-operation compliance mitigation measures, including the following:

Mitigation Measure SS-9: Establishment of a cooperative organization of pipeline operators to facilitate oil spill response.

Mitigation Measure S-13: Preparation of an Oil Spill Contingency Plan.

Mitigation Measure SS-13/ML-7: Storage locations for oil spill response equipment.

Mitigation Measure SS-22: Preparation of a Fire Protection Plan for pipeline operations.

Mitigation Measure SS-32: Aerial and on-ground pipeline leak and hazard detection.

Mitigation Measure SS-45: Cathodic protection.

Mitigation Measure A-19: Reduction of fugitive losses from flanges, valves, and seals.

The subject compliance submittals are currently under review and additional submittals are pending. Decisions by the Lead Agencies as to the adequacy of each pre-operation compliance submittal will be required prior to the commencement of pipeline operations.

CONSTRUCTION SCHEDULE

Table 12 presents the current construction schedule for Pacific Pipeline.

Table 12. Construction Segment Schedule

Segment

Original Construction Schedule

Revised Construction Start Date

Estimated Construction Completion Date1

Segment 1

July 1, 1997

Under construction since November 5, 1997

October 16, 1998

Segment 2A2

June 2, 1997

Erosion repairs, valve & conduit completion, & revegetation underway since June 18, 1998

August 15, 19984,5

Segment 2B

Mid-August, 1997

Under construction since November 6, 1997

October 18, 1998

Segment 2C3

Originally scheduled for completion as part of Segment 2A

Under construction since June 22, 1998

September 18, 19984,5

Segment 3

July 1, 1997

Under construction since September 30, 1997

October 11, 1998

Segment 4A

July 1, 1997

Under construction since October 20, 1997

September 15, 1998

Segment 4B

August 25, 1997

Under construction since October 23, 1997

September 16, 19984

Segment 5

July 1, 1997

Under construction since July 14, 1997

October 1, 19984

Emidio Pump Station

October 1997

Under construction since June 11, 1998

July 29, 19984

Grapevine Pump Station  

Under construction since June 29, 1998

July 29, 19984

Whitaker Pressure Relief Station  

Under construction since first week of September 1998

September 27, 19986

Lynwood Station  

Under construction since September 12, 1998

October 22, 19986

El Segundo  

Under construction since September 28, 1998

October 21, 19986

Wilmington  

October 1998

October 31, 19986

Ultramar  

October 1998

August 14, 19984,7

1. Estimated construction schedule per PPSI, July 23, 1998 (segments only).
2. Initial construction completed from June 27 through November 9, 1997.
3. Templin Highway to ANF southern boundary.
4. Construction has not been completed as planned.
5. USFS, ANF, requiring completion of construction within the ANF by October 3, 1998.
6. Estimated station completion schedule per PPSI, August 24, 1998 memorandum.
7. Not included in August 24, 1998 memorandum from PPSI.

 

PUBLIC ACCESS PROGRAM

• Due to the lack of public interest in visiting the MMCRP Walk-In Sites (that was in operation from July 1997 through February 1998), our Student Interns no longer staff the Valley Family Center site in San Fernando, and the Parents of Watts site in Watts on a scheduled basis. However, project documents and PPSI computers remain at the sites for public use, and MMCRP Student Interns available on an as-needed basis (i.e., by appointment). The project information hotline and project newsletter, provide information on how to make an appointment for the Walk-In Sites

• During September, no members of the public made appointments to visit the MMCRP Walk-In sites in San Fernando and Watts.

• The hotline message and project web site continue to be updated as the project progresses. During September, no messages were left on the hotline, and the web site received 164 hits.

Environmental Justice: As of September, PPSI is in compliance with all construction-related aspects of the mitigation measures applicable to minority populations and low-income populations. These measures include: ML-1 (Community Outreach and Communications Program), ML-2 (Community Partnership Program), ML-3 (Local Community and MBE Hiring Program), and ML-6 (implementation of the BIMP).

Back to MMCRP Home page