Daily Report

CPUC/ANF Environmental Monitoring Activities

Pacific Pipeline Construction Project

Aspen Environmental Group Friday, January 22, 1999
   

The following is a brief summary of the environmental monitoring activities that were completed between January 22, 1999 1:00 and 1:00 on January 23, 1999. This summary is based on reports directly received from the field and has not been edited. If you have any questions please contact (818) 597-3407. Please note the item number and the correction that should be made. This report is intended to serve as a communication document and as an instrument for quality control.

Construction Highlights

01/22/99 (Friday)

 Segment 5 (Lynwood to Long Beach): Report for 1-22-99. Crews coated pipe and conducted a general clean up at the Edison site near EMP 113.5. Further, crews working nearby placed and concreted fence posts along the rail road right of way. Trenching began along the Huntway section south of Tosco however progress was hindered due to a lack of shoring materials. In addition, crews potholed and x-rayed several sections of pipe. At Tosco crews completed the bore pit, delivered the boring machine with concrete pipe and welded the 16'' tie-in for the Huntway lateral. Commission crews and electricians progressed with the Tosco check list. Segment 4B (Lynwood to El Segundo): Crews at Lynwood station continued clean up and installation of the roof eye brow for the site.

Inspection Summar

In the past 24 hours, 1 inspection event(s) were reported for 1 spread(s). Of these inspections, 0 were non-compliance event(s). Also 0 non-compliance resolution report(s) was resolved.

Non-Compliance Reports (NCR's) Issued

No new non-compliance reports were issued during the last reporting period.

Non-Compliance Resolution Reports (NCRR's) Issued

No new non-compliance reports were issued during the last reporting period.

Summary of Follow-up Items for Today

No follow-up items were reported for today.