Daily Report

CPUC/ANF Environmental Monitoring Activities

Pacific Pipeline Construction Project

Aspen Environmental Group Sunday, November 15, 1998

The following is a brief summary of the environmental monitoring activities that were completed on November 15, 1998. This summary is based on reports directly received from the field and has not been edited. If you have any questions please contact (818) 597-3407. Please note the item number and the correction that should be made. This report is intended to serve as a communication document and as an instrument for quality control.

Construction Highlights

11/15/98 (Sunday)

Segment 5 (Lynwood to Long Beach) Report for 15 November 1998: The directional drill crew work pushing the 36-inch reamer. Progress was approximately 60 feet per hour.

Inspection Summary

In the past 24 hours, 5 inspection event(s) were reported for 5 spread(s). Of these inspections, 0 were non-compliance event(s). Also 0 non-compliance resolution report(s) was resolved.

Non-Compliance Reports (NCR's) Issued

No new non-compliance reports were issued during the last reporting period.

Non-Compliance Resolution Reports (NCRR's) Issued

No new non-compliance reports were issued during the last reporting period.

Summary of Follow-up Items for Today

No follow-up items were reported for today.