Daily Report

CPUC/ANF Environmental Monitoring Activities

Pacific Pipeline Construction Project

Aspen Environmental Group Sunday, December 20, 1998
   

The following is a brief summary of the environmental monitoring activities that were completed on December 20, 1998. This summary is based on reports directly received from the field and has not been edited. If you have any questions please contact (818) 597-3407. Please note the item number and the correction that should be made. This report is intended to serve as a communication document and as an instrument for quality control.

Construction Highlights

12/20/98 (Sunday)

Segment 1 report for 12/20/98: Cleaner pigs were run through the segment of pipe beginning at Emidio Pump Station (EMP 0.00) to the north side of the California Aqueduct bore (EMP 12.20). Welding, x-ray and coating occurred at the tie-in on the south side from EMP 12.28 to 12.34.

Inspection Summar

In the past 24 hours, 1 inspection event(s) were reported for 1 spread(s). Of these inspections, 0 were non-compliance event(s). Also 0 non-compliance resolution report(s) was resolved.

Non-Compliance Reports (NCR's) Issued

No new non-compliance reports were issued during the last reporting period.

Non-Compliance Resolution Reports (NCRR's) Issued

No new non-compliance reports were issued during the last reporting period.

Summary of Follow-up Items for Today

No follow-up items were reported for today.

Back to Daily Reports