March 24, 1998

Dean Shauers, Project Manager
Pacific Pipeline System, Inc.
12201 E. Arapahoe Road, C10
Englewood, CO 80112

RE: Variance Request #58 - Allow for 24-hour construction, seven days a week, at the "Dog Pound" directional drill sites, City of Burbank (Segment 3).

Clearance #28 (amendment) - 45 day time extension for completion of directional drill operations at the "Dog Pound" sites, City of Burbank (Segment 3).

Dear Mr. Shauers:

We have reviewed the above-referenced requests and approve your requests, based on the following factors:

- All applicable mitigation measures for the project shall be implemented at the subject location.

- Written approval from the City of Burbank granting 24-hour construction, seven days a week, shall be submitted to the CPUC Lead Environmental Monitor prior to the commencement of such construction.

- All businesses within 500 feet of the directional drill sites shall be notified of the proposed 24-hour construction, seven days a week, prior to the commencement of such construction. All noise complaints received shall be filed immediately with the City of Burbank and CPUC Lead Environmental Monitor for consideration. Failure to file any noise complaints shall result in the immediate cessation of construction as granted under this variance approval.

- Implementation of this variance in accordance with the provisions noted above shall be verified on a random basis by a CPUC/ANF Environmental Monitor.

Sincerely,

Andrew Barnsdale
Project Manager

 

cc: R. Borden, ANF
H. Rastegar, Aspen