Daily Report |
![]() |
CPUC Environmental Monitoring Activities |
SFPP Carson to Norwalk Project |
| Aspen Environmental Group | Sunday, May 2, 1999 |
Construction Highlights
Spread 1
City of Long Beach
Spread 1 work in the City of Long Beach has been completed.
City of Paramount
No Spread 1 work occurred in the City of Paramount during the shift.
City of Bellflower
No work occurred in the City of Bellflower during the shift.
City of Cerritos
Variance request #8 was approved by the CPUC, allowing the applicant to work on Sunday May 2nd and Sunday May 9th at the San Gabriel River. The crew at the San Gabriel River replaced the augers and started pushing casing again after clearing the alignment of old casing. The crew pushed approximately 90 feet of 30-inch casing pipe during the shift. The bore is on the correct alignment laterally and within 1-foot vertically.
City of Artesia
No work occurred in the City of Artesia during the shift.
City of Norwalk
No work occurred in the City of Norwalk during the shift.
Spread 2
Los Angeles County
No work occurred in Los Angeles County during the shift.
City of Long Beach
No work occurred in the City of Long Beach during the shift.
City of Paramount
No work occurred in the City of Paramount during the shift.
Watson Station
City of Carson
No work occurred at the Watson Station during the shift.
Industry Station
City of Walnut
No work occurred in the Watson Station during the shift.
End of Report