Daily Report

wpe7.gif (6380 bytes)

CPUC Environmental Monitoring Activities

SFPP Carson to Norwalk Project

Aspen Environmental Group Sunday, May 2, 1999

The following is a brief summary of the environmental monitoring activities that were completed between 1:00 on 5/2/99 and 1:00 on 5/03/99. This summary is based on reports directly received from the field and has not been edited. If you have any questions please contact (818) 597-3407. This report is intended to serve as a communication document and as an instrument for quality control.


Construction Highlights

 

Spread 1

City of Long Beach

Spread 1 work in the City of Long Beach has been completed.

City of Paramount

No Spread 1 work occurred in the City of Paramount during the shift.

City of Bellflower

No work occurred in the City of Bellflower during the shift.

City of Cerritos

Variance request #8 was approved by the CPUC, allowing the applicant to work on Sunday May 2nd and Sunday May 9th at the San Gabriel River. The crew at the San Gabriel River replaced the augers and started pushing casing again after clearing the alignment of old casing. The crew pushed approximately 90 feet of 30-inch casing pipe during the shift. The bore is on the correct alignment laterally and within 1-foot vertically.

City of Artesia

No work occurred in the City of Artesia during the shift.

City of Norwalk

No work occurred in the City of Norwalk during the shift.

Spread 2

Los Angeles County

No work occurred in Los Angeles County during the shift.

City of Long Beach

No work occurred in the City of Long Beach during the shift.

City of Paramount

No work occurred in the City of Paramount during the shift.

Watson Station

City of Carson

No work occurred at the Watson Station during the shift.

Industry Station

City of Walnut

No work occurred in the Watson Station during the shift.

End of Report