![]() |
Daily Report |
![]() |
CPUC Environmental Monitoring Activities |
SFPP Carson to Norwalk Project |
| Aspen Environmental Group | Friday, May 14, 1999 |
Construction Highlights
Spread 1
City of Long Beach
Spread 1 work in the City of Long Beach has been completed.
City of Paramount
No Spread 1 work occurred in the City of Paramount during the shift.
City of Bellflower
The electrical crew continued to set the conduit from the valve on the west side of the San Gabriel River.
City of Cerritos
No work occurred on the east side of the San Gabriel River except for the repacking of the valve.
City of Artesia
No work occurred in the City of Artesia during the shift.
City of Norwalk
No work occurred in the City of Norwalk during the shift.
Spread 2
Los Angeles County
The backfilling crew worked on the north side of Compton Creek during the shift. The crew poured the concrete sidewalk and river bank and repaired sections of the curb that were damaged during construction. A small crew replaced the fencing on the bank of Compton Creek and attached the pedestrian barrier on the suspended pipe.
City of Long Beach
The trench has been backfilled to grade at DeForest Park with the exception of the valve site. No other work occurred in the Park.
City of Paramount
No work occurred in the City of Paramount during the shift.
Watson Station
City of Carson
The crew at the Watson Station is not scheduled to work on Fridays. A small crew monitored the valve and hydrostatic testing graph and gauges at the west end of the line. The pressure held at 1400 psi and the line was pressurized to the test pressure of 1820 psi. The line held the full test pressure with no drops for the duration of the eight-hour hydrostatic test.
Norwalk Station
City of Norwalk
The crew at the Norwalk Station started bringing the line up to pressure for the hydrostatic test. The line pressurized to 1400 psi when problems with the valves were noticed. The applicant stopped the test and the eight valves were inspected. The valve housings were repacked and the hydrostatic test resumed at 3:00 PM.
Colton Station
City of Colton
The electrical crews worked at the valves and junction boxes at the Colton Station. No other construction crews worked at the station during the shift.
End of Report