Aspen Environmental Group Wednesday, May 19, 1999

The following is a brief summary of the environmental monitoring activities that were completed between 1:00 on 5/19/99 and 1:00 on 5/20/99. This summary is based on reports directly received from the field and has not been edited. If you have any questions please contact (818) 597-3407. This report is intended to serve as a communication document and as an instrument for quality control.


Construction Highlights

Spread 1

City of Long Beach

Spread 1 work in the City of Long Beach has been completed.

City of Paramount

No Spread 1 work occurred in the City of Paramount during the shift.

City of Bellflower

No work occurred on the west side of the San Gabriel River.

City of Cerritos

The backfilling crew poured slurry around the valve on the east side of the San Gabriel River. The crew cleaned the right-of-way and worked on the grade at the bore pit. The applicant was informed of further clean-up of the adjacent buildings required.

City of Artesia

The final paving crew has completed work in the City of Artesia.

City of Norwalk

No work occurred in the City of Norwalk during the shift.

Spread 2

Los Angeles County

A small crew worked at Compton Creek to clean-up the right-of-way and patch small holes in the asphalt adjacent to the railroad tracks.

City of Long Beach

The electrical crew worked on the power connections on the west side of the Los Angeles River during the shift.

City of Paramount

The final paving crew continued work on Madison Street in the City of Paramount during the shift.

Watson Station

City of Carson

The crew at the Watson Station continued working on the electrical connections and on small diameter lines. A section of pipe was welded on in the Watson yard to divert the cleaning pigs into a catcher. The contractor enclosed the receiving area and sprayed water over the area to minimize fugitive dust. The crew worked until 10:00 PM at the Watson Station.

Norwalk Station

City of Norwalk

The crew at the Norwalk Station worked on clean-up and a small crew launched the cleaning pigs through the 16-inch line to the Watson Station.

Industry Station

City of Industry

A small crew moved to the Industry Station to start excavation for the connections to the proposed motors and valves.

End of Report