Construction Highlights
Spread 1
City of Long Beach
Spread 1 work in the City of Long Beach has been completed.
City of Paramount
No Spread 1 work occurred in the City of Paramount during the shift.
City of Bellflower
No work occurred on the west side of the San Gabriel River.
City of Cerritos
The backfilling crew poured slurry around the valve on the east side of the San Gabriel River. The crew cleaned the right-of-way and worked on the grade at the bore pit. The applicant was informed of further clean-up of the adjacent buildings required.
City of Artesia
The final paving crew has completed work in the City of Artesia.
City of Norwalk
No work occurred in the City of Norwalk during the shift.
Spread 2
Los Angeles County
A small crew worked at Compton Creek to clean-up the right-of-way and patch small holes in the asphalt adjacent to the railroad tracks.
City of Long Beach
The electrical crew worked on the power connections on the west side of the Los Angeles River during the shift.
City of Paramount
The final paving crew continued work on Madison Street in the City of Paramount during the shift.
Watson Station
City of Carson
The crew at the Watson Station continued working on the electrical connections and on small diameter lines. A section of pipe was welded on in the Watson yard to divert the cleaning pigs into a catcher. The contractor enclosed the receiving area and sprayed water over the area to minimize fugitive dust. The crew worked until 10:00 PM at the Watson Station.
Norwalk Station
City of Norwalk
The crew at the Norwalk Station worked on clean-up and a small crew launched the cleaning pigs through the 16-inch line to the Watson Station.
Industry Station
City of Industry
A small crew moved to the Industry Station to start excavation for the connections to the proposed motors and valves.
End of Report