Delivered Energy
During 2008, SGIP projects delivered over 718,000 MWh of electricity to California’s grid.
Thermal cogeneration systems (fuel cells, engines, and turbines) provided over 63% of the electricity. Photovoltaic projects were the second largest supplier at 27%.
PG&E was again the largest utility contributor, providing over 40% of the total energy delivered.
Peak Demand
Total SGIP project capacity coincident with the 2008 CAISO peak was over 141 MW representing an aggregate peak hour impact of 0.44 kWh per kW of rebated capacity.
Of the eligible technologies, gas turbines showed the highest peak capacity factor of 0.84 kWh of peak capacity per kWh of rebated capacity, followed by PV at 0.59 kWh per kW.
Transmission and Distribution System
PV technologies showed afternoon peak reduction factors for PV ranging from 42 percent to 63 percent.
These factors equate to the kW of peak reduction per kW of rebated PV.
The absolute peak loading reduction was found to be small due to the low penetration of SGIP technologies. However, increased SGIP installations and the inclusion of advanced energy storage systems should both increase the benefits of SGIP.