Word Document PDF Document

PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

ENERGY DIVISION RESOLUTION E-4073

RESOLUTION

Resolution E-4073. San Diego Gas & Electric (SDG&E) Company requests approval of four renewable resource procurement contracts resulting from its 2005 RPS solicitation. These contracts are approved with modifications.

By Advice Letter 1845-E filed on November 20, 2006.

______________________________________________________________________

SUMMARY

SDG&E's renewable contracts comply with the Renewable Portfolio Standard (RPS) procurement guidelines and are approved with modifications

SDG&E's renewable contracts comply with the Renewable Portfolio Standard (RPS) procurement guidelines and are approved SDG&E's request for approval of the renewable resource procurement contracts (Bull Moose, Esmeralda-San Felipe, Bethel Solar 1 and Bethel Solar 2) are granted pursuant to D.05-07-039. The energy acquired from these contracts will count towards SDG&E's Renewable Portfolio Standard (RPS) requirements.

Facility

Tech

Term

MW

GWh

COD

Location

Bull Moose

Biomass

20

20

158

12/08

San Diego

Esmeralda- San Felipe

Geothermal

15

20

166

12/10

Imperial Valley

Bethel

Solar 1

Solar Thermal

20

49.4

168

06/08

Imperial Valley

Bethel

Solar 2

Solar Thermal

20

49.4

168

12/08

Imperial Valley

In addition, the contract prices for each contract, which are at or below the Market Price Referent, are fully recoverable in rates over the life of the contracts, subject to Commission review of SDG&E's administration of the contracts. Because deliveries from these power purchase agreements (PPA) are priced below the 2005 market price referent (MPR), they do not require supplemental energy payments (SEPs) from the California Energy Commission (CEC).

Confidential information about the contract should remain confidential

This resolution finds that certain material filed under seal pursuant to Public Utilities (Pub. Util.) Code Section 583 and General Order (G.O.) 66-C should be kept confidential to ensure that market sensitive data does not influence the behavior of bidders in future RPS solicitations.

BACKGROUND

The RPS Program requires each utility to increase the amount of renewable energy in its portfolio

The California Renewables Portfolio Standard (RPS) Program was established by Senate Bill 1078, effective January 1, 2003. It requires that a retail seller of electricity such as SDG&E purchase a certain percentage of electricity generated by Eligible Renewable Energy Resources (ERR). The RPS program is set out at Public Utilities Code Section 399.11, et seq. Each utility is required to increase its total procurement of ERRs by at least 1% of annual retail sales per year so that 20% of its retail sales are supplied by ERRs by 2017.

The State's Energy Action Plan (EAP) called for acceleration of this RPS goal to reach 20 percent by 2010. This was reiterated again in the Order Instituting Rulemaking (R.04-04-026) issued on April 28, 2004.1 On September 26, 2006, Governor Schwarzenegger signed Senate Bill 107 (SB 107, Chapter 464, Statutes of 2006), which officially accelerates the State's RPS targets to 20 percent by 2010. The bill went into effect on January 1, 2007.

In addition, the Commission established an APT for each utility, which consists of two separate components: the baseline, representing the amount of renewable generation a utility must retain in its portfolio to continue to satisfy its obligations under the RPS targets of previous years; and the incremental procurement target2 (IPT), defined as at least one percent of the previous year's total retail electrical sales, including power sold to a utility's customers from its DWR contracts.

R.04-04-026 established procurement guidelines for the RPS Program

The Commission has issued a series of decisions that established the regulatory and transactional parameters of the utility renewables procurement program. On June 19, 2003, the Commission issued its "Order Initiating Implementation of the Senate Bill 1078 Renewable Portfolio Standard Program," D.03-06-071. On June 9, 2004, the Commission adopted its Market Price Referent methodology3 for determining the Utility's share of the RPS seller's bid price, as defined in Public Utilities Code Sections 399.14(a)(2)(A) and 399.15(c). On the same day the Commission adopted standard terms and conditions for RPS power purchase agreements in D.04-06-014 as required by Public Utilities Code Section 399.14(a)(2)(D). Instructions for evaluating the value of each offer to sell products requested in a RPS solicitation were provided in D.04-07-029.

SDG&E requests approval of a new renewable energy contract

On November 20, 2006, SDG&E filed Advice Letter (AL) 1845-E requesting Commission approval of four renewable procurement contracts: Bull Moose, Esmeralda-San Felipe, Bethel Solar 1 and Bethel Solar 2. These PPAs result from SDG&E's September 30, 2005 solicitation for renewable bids, which was authorized by Decision D.05-07-039.

The Commission's approval of this PPA will contribute significantly towards SDG&E's renewable procurement goals. In 2005, the year of this RPS solicitation, SDG&E's IPT was approximately 158 GWh. Once all the projects are generating, the PPAs will contribute an incremental aggregate of approximately 660 GWh per year, approximately 500 GWh of which are planned to be delivered in 2010.4

SDG&E requests final "CPUC Approval" of PPAs

SDG&E requests the Commission to issue a resolution containing the findings required by the definition of "CPUC Approval" in Appendix A of D.04-06-014. In addition, SDG&E requests that the Commission issue a resolution that approves for each of the four PPAs:

1. The PPA is approved in its entirety, including payments to be made by SDG&E, subject to CPUC review of SDG&E's administration of the PPA. Costs to SDG&E may include items such as congestion and transmission upgrades.

2. Any procurement pursuant to this PPA is procurement from an eligible renewable energy resource for purposes of determining SDG&E's compliance with any obligation that it may have to procure eligible renewable energy resources pursuant to the California Renewables Portfolio Standard (Public Utilities Code Section 399.11 et seq.), D.03-06-071, or other applicable law;

3. Any procurement pursuant to this PPA constitutes incremental procurement or procurement for baseline replenishment by SDG&E from an eligible renewable energy resource for purposes of determining SDG&E's compliance with any obligation to increase its total procurement of eligible renewable energy resources that it may have pursuant to the California Renewables Portfolio Standard, CPUC D.03-06-071, or other applicable law.

4. Any costs associated with the rebalancing of SDG&E's capital structure due to the impacts of FIN 46 or debt equivalence obligations shall be recoverable.

SDG&E's Procurement Review Group participated in review of the contracts

In D. 02-08-071, the Commission required each utility to establish a "Procurement Review Group" (PRG) whose members, subject to an appropriate non-disclosure agreement, would have the right to consult with the utilities and review the details of:

The PRG for SDG&E consists of: California Department of Water Resources (DWR), the Commission's Energy Division, Natural Resources Defense Council (NRDC), Union of Concerned Scientists (UCS), Division of Ratepayer Advocates (DRA), and The Utility Reform Network (TURN).

SDG&E periodically met with its PRG to brief them during the course of LCBF analysis, shortlist development and negotiation. SDG&E first briefed its PRG on December 5, 2005, regarding SDG&E's preliminary assessment of the bids received in response to the 2005 RFO. SDG&E provided further briefings on January 24, 2006, to summarize its recommendations for a preliminary shortlist.

On March 24, 2006, SDG&E briefed the PRG on its final shortlist and provided an update on the status of its negotiations. The March 24th meeting included a summary of the terms of the Bull Moose PPA, the Esmeralda-San Felipe PPA, the Bethel Solar 1 PPA and the Bethel Solar 2 PPA. On June 13, 2006, SDG&E provided further analysis of the final shortlist to the PRG, including contributions to the 20% RPS target and summaries of the qualitative and quantitative factors used to evaluate each project on the shortlist. SDG&E provided an additional update regarding the 2005 final shortlist.

None of the PRG members have expressed any objection to the price or terms presented to them in connection with the Proposed PPAs. Although Energy Division is a member of the PRG, it reserved its conclusions for review and recommendation on the contracts to the resolution process.

Although Energy Division is a member of the PRG, it reserved its judgment on the contracts until the resolution process. Energy Division reviewed the transactions independent of the PRG, and allowed for a full protest period before concluding its analysis.

NOTICE

Notice of AL 1845-E was made by publication in the Commission's Daily Calendar. SDG&E states that a copy of the Advice Letter was mailed and distributed in accordance with Section III-G of General Order 96-A.

PROTESTS

AL 1845-E was not protested.

DISCUSSION

Description of the projects

The following table summarizes the substantive features of the PPAs. See confidential Appendix B for a detailed discussion of contract prices, terms, and conditions:

Facility

Tech

Term

MW

GWh

COD

Location

Bull Moose

Biomass

20

20

158

12/08

San Diego

Esmeralda- San Felipe

Geothermal

15

20

166

12/10

Imperial Valley

Bethel

Solar 1

Solar Thermal

20

49.4

168

06/08

Imperial Valley

Bethel

Solar 2

Solar Thermal

20

49.4

168

12/08

Imperial Valley

PPAs are consistent with SDG&E's CPUC adopted 2005 RPS Plan

California's RPS statute (SB 107) requires the Commission to review the results of a renewable energy resource solicitation submitted for approval by a utility. The Commission will then accept or reject proposed PPAs based on their consistency with the utility's approved renewable procurement plan (Plan). On September 7, 2005 the Energy Division notified SDG&E that no protests were received in response to its revised 2005 plan and authorized SDG&E to issue its 2005 RFO. The Proposed PPA's are consistent with SDG&E's Commission-approved RPS plan.

PPAs fit with identified renewable resource needs and are consistent with RPS Solicitation Protocol

SDG&E's 2005 RPS plan called for SDG&E to issue competitive solicitations for eligible renewable resources from both large-scale generation projects and small, distributed renewable projects. The solicitations were entitled: "Eligible Renewable Resources" and "Distributed Renewable Technologies." Both solicitations were issued on September 30, 2005 and responses were due on November 1, 2005. Offers from both solicitations were evaluated collectively under one LCBF analysis. One short list was created that encompassed offers from both RFOs.

For Eligible Renewable Resources, SDG&E sought large-scale generation for as-available or unit-firm capacity and/or energy from:

In order to submit proposals under the solicitation, the Projects had to have participated in the 2005 Transmission Ranking Cost Report ("TRCR") study applicable to the specific utility's transmission grid to which each of the Projects will tie-in. Responses from Respondents who had system impact studies approved by the CAISO were also acceptable and deemed in conformance of the RFO.

The RFO provided that Respondents could offer 10, 15 or 20-year PPAs with

deliveries commencing in 2006, 2007 or 2008. Resources located in Imperial

Valley were required to commence in 2010, unless the resource had adequate

transmission capability to deliver to SP-15 sooner. The RFO required that any

PPA executed for resources from Imperial Valley without such adequate

transmission capability be contingent upon SDG&E obtaining approval for and

being able to license and construct a new 500 kV line from Imperial Valley to the San Diego area.

In addition to the PPAs described above, Respondents offering new renewable

resources were also allowed to provide an option price for SDG&E to acquire the facility along with all environmental attributes, land rights, permits and other licenses - thus enabling SDG&E to own and operate the facility at the end of the PPA term.

Finally, Respondents were allowed to propose turnkey projects to develop,

permit, and construct new, RPS-eligible generating facilities to be acquired by

SDG&E. The same transmission contingency applied to turnkey projects as to

PPA offers. An open and competitive playing field was established for the procurement effort.

Bid evaluation process consistent with Least-Cost Best Fit (LCBF) decision

SDG&E evaluated all offers in accordance with the LCBF process outlined in D.03-06-071 and D.04-07-029.

Bid Evaluation Process

Upon conclusion of the bidding process, SDG&E performed an initial screening to determine if each bid met minimum requirements of the RFO. Each bid was required to be received by the RFO deadline and must have included all required documentation. Bids not received by the RFO deadline (unless there was a technical difficulty and notification was received by SDG&E prior to the deadline) were disqualified. Once SDG&E had a list of viable projects, SDG&E began to narrow the field of bidders for its short list. For its LCBF analysis, SDG&E assessed various cost elements associated with a qualified offer, including average all-in bid price, transmission cost adders, congestion

cost/benefit and Reliability Must Run ("RMR") benefits. The following describes how SDG&E determined each of the cost elements:

Once all cost elements were determined, SDG&E summed up the four $/MWh cost elements in 2006 dollars to determine the overall unit cost ("OUC") of a proposed project for ranking purposes. SDG&E ranked each OUC in the order of least cost. Those projects with acceptable OUC's were initially shortlisted.

Portfolio Fit

SDG&E's 2005 plan stated that SDG&E does not have a preference for a particular product or technology type and that SDG&E has latitude in the resources that it selects. The Projects, therefore, were not selected due to a pre-determined preference for the product type or technology type. SDG&E fairly reviewed all offers and selected the Projects due to factors applicable to its LCBF analysis, as explained above.

Consistent Application of Time of Delivery ("TOD") Factors

In its solicitation documents, SDG&E notified potential Respondents that "SDG&E is utilizing Time of Delivery TOD factors for non-baseloaded resources." During its LCBF evaluation, SDG&E applied TOD factors to all offers with intermittent products such as wind and solar. The average all-in bid price, as described above, was adjusted to reflect the relative value of projected energy deliveries during peak, semipeak and off-peak periods. The projected delivery profiles were provided by the Respondents.

Qualitative Factors

As stated in the RFO, SDG&E differentiates offers of similar cost by reviewing qualitative factors including (in no particular order of preference):

Minority/low-income areas and environmental stewardship were not factors in SDG&E's ranking process because those factors were not applicable to the offers. However, SDG&E did consider its own service territory and resource diversity in its ranking.

Consistency with Adopted Standard Terms and Conditions

D.04-06-014 adopted standard RPS contract terms and conditions to be used in RPS PPAs. The decision identified certain terms as either modifiable or non-modifiable. All non-modifiable terms and conditions in each of the proposed PPAs are consistent with D.04-06-014.

Contract prices are at or below the 2005 MPR

The contract prices for each of the Proposed PPAs are at or below the 2005 MPR prices as set forth in Resolution E-3980 issued on April 13, 2006. Therefore, the proposed PPAs do not require Supplemental Energy Payments.

PPAs are viable projects

SDG&E believes that the projects are viable because:

Financing

SDG&E expects that each of the Projects will be able to obtain adequate and timely financing to allow such Projects to deliver by their Commercial Operation deadlines.

Creditworthiness and Experience

Each of the Proposed PPAs contains performance securities that will motivate the respective developers to declare Commercial Operation by the respective deadlines and perform in accordance with all terms and conditions. In addition, each developer has prior experience developing projects similar to those contemplated by their respective PPAs.

Transmission

Site Control

Permitting

Technology

Production or Investment Tax Credits

The Proposed PPAs are not contingent on Production Tax Credits. However, the Bethel Solar 1 PPA and the Bethel Solar 2 PPA pricing terms are both contingent on Investment Tax Credits and accelerated depreciation benefits (though all price options for the projects are below the MPR).

Cost recovery for debt equivalence and FIN 46(R) requirements associated with these contracts will not be addressed in this Resolution

In AL 1845-E, SDG&E requests Commission approval by resolution for recovery of any costs associated with the rebalancing of SDG&E's capital structure due to the impacts of FIN 46 or debt equivalence obligations. Pursuant to D.07-02-011, pp.29-31, such ratemaking relief may not be made via resolution, but instead may be addressed in the IOUs' cost of capital proceedings.

Confidential information about the contracts should remain confidential

Certain contract details were filed by SDG&E under confidential seal. Energy Division recommends that certain material filed under seal pursuant to Public Utilities (Pub. Util.) Code Section 583, General Order (G.O.) 66-C, and D.06-06-066, and considered for possible disclosure, should be kept confidential to ensure that market sensitive data does not influence the behavior of bidders in future RPS solicitations.

COMMENTS

This is an uncontested matter in which the decision grants the requested relief with only minor modifications.  Therefore, pursuant to Public Utilities Code § 311(g)(2), the otherwise applicable 30-day period for public review and comment was shortened to 10 days (6 days for comments and an additional 4 days for reply comments). No comments or reply comments were received for draft Resolution E-4073.

FINDINGS

1) SDG&E filed Advice Letter 1845-E on November 20, 2006, requesting Commission review and approval of four new renewable energy contracts: Bull Moose, Esmeralda-San Felipe, Bethel Solar 1 and Bethel Solar 2.

2) The RPS Program requires each utility, including SDG&E, to increase the amount of renewable energy in its portfolio to 20 percent by 2010, increasing by a minimum of one percent per year.

3) On September 7, 2005 the Energy Division notified SDG&E that no protests were received in response to its revised 2005 plan and authorized SDG&E to issue its 2005 RFO.

4) SDG&E issued its 2005 RPS RFO on September 30, 2005.

5) D.04-06-014 set forth standard terms and conditions to be incorporated into RPS PPAs.

6) Levelized contract prices at or below the 2005 MPR are considered per se reasonable as measured according to the net present value calculations explained in D.04-06-015 and D.04-07-029.

7) D.04-07-029 adopted least-cost, best-fit criteria which the utilities must use in their selection process after the RFO has been closed.

8) The Commission required each utility to establish a Procurement Review Group (PRG) to review the utilities' interim procurement needs and strategy, proposed procurement process, and selected contracts.

9) SDG&E first briefed its PRG on December 5, 2005, regarding SDG&E's preliminary assessment of the bids received in response to the 2005 RFO. SDG&E provided further briefings on January 24, 2006, to summarize its recommendations for a preliminary shortlist. On March 24, 2006, SDG&E briefed the PRG on its final shortlist and provided an update on the status of its negotiations. None of the PRG members have expressed any objection to the price or terms presented to them in connection with the Proposed PPAs.

10) Certain material filed under seal pursuant to Public Utilities (Pub. Util.) Code Section 583, General Order (G.O.) 66-C, and D.06-06-066, and considered for possible disclosure, should not be disclosed. Accordingly, the confidential appendices, marked "[REDACTED]" in the redacted copy, should not be made public upon Commission approval of this resolution.

11) The proposed contract prices are at or below the 2005 MPRs released in Resolution E-3980 issued on April 13, 2006.

12) The Commission has reviewed the proposed contracts and finds them to be consistent with SDG&E's approved 2005 renewable procurement plan.

13) Procurement pursuant to the PPAs are procurement from an eligible renewable energy resource for purposes of determining SDG&E compliance with any obligation that it may have to procure eligible renewable energy resources pursuant to the California Renewables Portfolio Standard (Public Utilities Code Section 399.11 et seq.), Decision 03-06-071, or other applicable law.

14) Procurement pursuant to the PPAs constitute incremental procurement or procurement for baseline replenishment by SDG&E from an eligible renewable energy resource for purposes of determining SDG&E's compliance with any obligation to increase its totals procurement of eligible renewable energy resources that it may have pursuant to the California Renewables Portfolio Standard (Public Utilities Code Section 399.11 et seq.), Decision 03-06-071, or other applicable law.

15) Any indirect costs of renewables procurement identified in Section 399.15(a)(2) shall be recovered in rates.

16) AL 1845-E should be approved with modifications today; per D.07-02-011 (pp. 29-31, CoL 9 and OP 2), SDG&E's request for recovery of costs from the rebalancing of SDG&E's capital structure due to the impacts of FIN 46 or debt equivalence obligations is not approved by advice letter, but is best addressed in a cost of capital proceeding.

THEREFORE IT IS ORDERED THAT:

1. Advice Letter AL 1845-E is approved with modifications.

2. This Resolution is effective today.

I certify that the foregoing resolution was duly introduced, passed and adopted at a conference of the Public Utilities Commission of the State of California held on March 15, 2007; the following Commissioners voting favorably thereon:

MICHAEL R. PEEVEY

PRESIDENT

DIAN M. GRUENEICH

JOHN A. BOHN

RACHELLE B. CHONG

TIMOTHY ALAN SIMON

Commissioners

Confidential Appendix A

Solicitation Analysis

REDACTED

Confidential Appendix B -1

Bull Moose Contract Summary

REDACTED

Confidential Appendix B -2

Esmeralda Contract Summary

REDACTED

Confidential Appendix B -3

Bethel Contract Summary

REDACTED

Confidential Appendix C

Contract Pricing Analysis

REDACTED

Confidential Appendix D

Projects' Contribution

Toward RPS Goals

REDACTED

1 http://www.cpuc.ca.gov/Published/Final_decision/36206.htm

2 IPT - The incremental procurement target (IPT) represents the amount of RPS-eligible procurement that the LSE must purchase in a given year, over and above the total amount the LSE was required to procure in the prior year. An LSE's IPT equals at least 1% of the previous year's total retail electrical sales, including power sold to a utility's customers from its DWR contracts.

3 D.04-07-015

4 The California Energy Commission is responsible for determining the RPS-eligibility of a renewable generator. See Public Utilities Code Sect. 399.12 and CPUC decision D.04-06-014.

Top Of Page