Crown Castle NG West
San Mateo County Project

Application No. A. 13-02-007

 

 

Back To Main Page

 

Welcome to the Mitigation Monitoring Compliance and Reporting Program page for the Crown Castle NG West (Crown Castle) – San Mateo County Project located along Highway 1 in San Mateo County, California.

Pursuant to the California Public Utilities Commission’s (CPUC) approval of the Project, Crown Castle is required to implement the Applicant Proposed Measures (APMs) identified in the Final Initial Study and Negative Declaration for the Crown Castle San Mateo County Project and the Mitigation Monitoring, Reporting, and Compliance Program (MMRCP).

The CPUC, as the CEQA lead agency, is responsible for ensuring that the APMs, as well as plans reviewed and approved by other agencies, are implemented throughout the construction phase of the Project. Below are project documents related to mitigation monitoring that are available for public review.

Quick Links

Mitigation Monitoring, Compliance and Reporting Program

Notice to Proceed

Environmental Monitoring Reports

Minor Project Refinement Requests

 

Mitigation Monitoring, Compliance and Reporting Program (MMCRP)

The program’s goal is to ensure compliance with applicant proposed measures approved in the Final Initial Study and Negative Declaration. Click on link below to view a complete copy of the MMCRP.

MMCRP

Notice to Proceed (NTP)

A NTP is issued contingent upon Crown Castle’s compliance with pre-construction requirements as specified by the approved APMs and responsible agency permitting requirements. A link to the approved pre-compliance reports, permit applications, and other documents is provided below.

Pre-compliance reports, permit applications, and other documents

Notice to Proceed

Description

NTP Request

NTP Approval

001

Construction of all project components

08/04/16

08/24/16


Environmental Monitoring Reports

A CPUC Environmental Monitor (EM) is monitoring construction activities to ensure that they are conducted in accordance with the approved APMs and permit conditions. Reports documenting construction status and compliance activities are provided below.

 

Weekly Report #

Reporting Period

Summary of Work Completed

Environmental Issues / Concerns

001

September 6 to 17, 2016

Mobilization, aerial installation, anchor/guy wire installation

No issues/concerns reported

002 September 18 to October 1, 2016 Aerial installation, anchor/guy wire installation, pole replacement No issues/concerns reported
003 October 2 to 15, 2016 Aerial installation, anchor/guy wire installation, pole replacement No issues/concerns reported
004 October 16 to 29, 2016 Aerial installation, anchor/guy wire installation, HDD installation No issues/concerns reported
005 October 30 to November 12, 2016 Aerial installation, anchor/guy wire installation, HDD installation Noticing signs not maintained; bicycle detours not provided
006 November 13 to 26, 2016 Aerial installation, anchor/guy wire installation, HDD installation Unauthorized trenching along Highway 1
007 November 27 to December 10, 2016 Aerial installation, anchor/guy wire installation, HDD installation Noticing signs not maintained; unauthorized trenching along Highway 1
008 December 11 to 24, 2016 Aerial installation, HDD installation Noticing signs not maintained
009 December 25, 2016 to January 7, 2017 Aerial installation Noticing signs not maintained
010 January 8 to 21, 2017 Aerial installation Noticing signs not maintained
011 January 22 to February 4, 2017 Aerial installation No issues/concerns reported
012 February 5 to 18, 2017 Aerial installation No issues/concerns reported
013 February 19 to March 10, 2017 Disturbed area restoration No issues/concerns reported

Minor Project Refinement Requests

The Commission decision approving the permit to construct authorizes Energy Division staff to approve requests by Crown Castle for minor project refinements. The decision states that the Energy Division may approve requests by Crown Castle for minor project refinements that may be necessary due to final engineering of the San Mateo County Project so long as such minor project refinements are located within the geographic boundary of the study area of the IS/ND and do not, without mitigation, result in a new significant impact or a substantial increase in the severity of a previously identified significant impact based on the criteria used in the environmental document; conflict with any mitigation measure or applicable law or policy; or trigger an additional permit requirement. Crown Castle shall seek any other project refinements by a petition to modify this decision.

Crown Castle's Minor Project Refinement Requests will be made available below when submitted to the CPUC.

For Additional Information

To access additional project information via the CPUC permitting website, please go to:
http://www.cpuc.ca.gov/environment/info/dudek/crowncastle/CrownCastleMain.htm

 

The CPUC’s Project Manager is:

Jensen Uchida, CPUC Project Manager
California Public Utilities Commission
505 Van Ness Avenue
San Francisco, CA 94102
Tel.: (415) 703-5484
 

Please report any problems to the Energy Division web coordinator.