IRP Procurement Track
The IRP "Procurement Track" was initiated in 2019, as ordered in D.19-04-040, to explore possible actions the Commission could take to address potential reliability or other procurement needs while the 2019-20 IRP cycle is underway.
Table 1. CPUC Procurement Orders (Applies to all CPUC-jurisdictional LSEs. No opt-outs allowed)
|
CPUC Orders |
Total |
2023 |
2024 |
2025 |
2026 |
2027 |
2028 |
2030 |
2031 |
2032 |
|
D.21-06-035 |
11,500 MW NQC |
2,000 by Aug |
6,000 by Jun 1 |
1,500 MW[1] by Jun 1 |
n/a[2] |
n/a |
2,000 MW by Jun 1 |
n/a |
n/a |
n/a |
|
D.23-02-040 |
4,000 MW NQC |
n/a |
n/a |
n/a |
2,000 MW by Jun 1 |
2,000 MW by Jun 1 |
n/a |
n/a |
n/a |
n/a |
|
D.26-02-057 |
6,000 MW NQC |
n/a |
n/a |
n/a |
n/a |
n/a |
n/a |
2,000 MW by Jun 1 |
2,000 MW by Jun 1 |
2,000 MW by Jun 1 |
|
Cumulative Procurement Ordered |
21,500 MW NQC |
2,000 MW |
6,000 MW |
1,500 MW |
2,000 MW |
2,000 MW |
2,000 MW |
2,000 MW |
2,000 MW |
2,000 MW |
Table 2. Timelines for CPUC Review of LSE Contracting
|
|
2023 |
2024 |
2025 |
2026 |
2027 |
2028 |
2029 |
2030 |
2031 |
2032 |
|
CPUC Reviews LSE Compliance Filings |
Feb 1, Aug 1, and Dec 1 |
Jun 3 and Dec 2 |
Jun 2 and Dec 1 |
Jun 1 and Dec 1 |
Jun 1 and Dec 1 |
Jun 1 and Dec 1 |
Jun 1 and Dec 3 |
Jun 3 and Dec 2 |
Jun 2 and Dec 1 |
Jun 1 and Dec 1 |
[1] D.21-06-035 required 2,500 of the 9,000 MW NQC required between 2023-2025 be “Diablo-Canyon Replacement.”
[2] D.21-06-035 required 2,000 MW NQC of Long-Lead Time Procurement by 2026, with an option to extend to 2028: 1,000 MW NQC of long-duration storage and 1,000 MW NQC of firm zero-emitting. D.23-02-040 automatically extends the procurement obligation to 2028. D.26-02-057 requires 6000 MW by 2032. 2000 MW each by June 2030, 2031, and 2032.
Procurement Progress:
IRP Procurement Compliance Summaries
- Procurement in Compliance with the Mid-Term Reliability (MTR, D.21-06-035) and Supplemental MTR (SMTR, D.23-02-040) per December 1, 2024 Filings, 7/10/2025
- Procurement in Compliance with D.19-11-016 and Mid Term Reliability (D.21-06-035) per December 1, 2023 Filings, 10/9/2024
- Procurement in Compliance with D.19-11-016 and Mid Term Reliability (D.21-06-035) per August 1, 2023 Filings, 4/22/2024
- Procurement in Compliance with D.19-11-016 and Mid Term Reliability (D.21-06-035) per February 1, 2023 Filings, 11/2/2023
- Procurement in Compliance with D.19-11-016 per August 1, 2022 Filings, 2/13/2023
- Procurement in Compliance with D.19-11-016 per February 1, 2022 Filings, 7/22/2022
- Procurement in Compliance with D.19-11-016 per February 1, 2021 Filings, 8/23/2021
Other Updates
- Overview of Tracking Energy Development (TED) Task Force, 5/20/2022
- Status of New Resources Expected, 11/23/2020
- LSEs' September 2019 Responses to Procurement Progress Data Request, 4/13/2020
- Summary of IOU IRP Reliability Procurement Track Public Progress Reports, 3/25/2020
- Summary of Self-Providing (non-IOU) IRP Reliability Procurement Track Public Progress Reports, 3/19/2020
Procurement Track Rulings and Decisions:
- D.26-02-057: Final Decision Ordering 2029-2032 Electric Resource Procurement (D.26-02-057), 2/26/2026
- Attachment A (Procurement Obligations), 2/26/2026
- Decision Fact Sheet, 2/26/2026
- Proposed Decision Ordering 2029-2032 Electric Resource Procurement, 1/14/2026
- Decision Fact Sheet, 1/14/2026
- Resolution E-5426: Final Resolution Adopting a Citation Program for Enforcing Compliance with Filing Deadlines and Reporting Requirements in the Integrated Resource Planning Proceedings, 10/30/2025
- D.25-09-007: Final Decision Granting, With Modifications, Southern California Edison Company's Petition for Modification of Decisions 23-02-040 and D.24-02-47, Bridge Contracts, 09/18/2025
- Administrative Law Judge’s Ruling Seeking Comments on Electricity Portfolios for 2026-2027 Transmission Planning Process and Need for Additional Reliability Procurement, 9/29/2025
- Slides on Need Determination Analysis, 9/29/2025
- D.25-06-005: Final Decision Granting, With Modifications, Long Duration Energy Storage Council's Petition for Modification of Decision 21-06-035, 06/17/2025
- Decision Fact Sheet, 7/23/2025
- D.24-09-006: Final Decision Allowing Bridge Resources for Alternative Compliance with Diablo Canyon Replacement Resource Category in Decision 21-06-035, 09/12/2024
- Decision Fact Sheet, 10/11/2024
- D. 23-02-040 Final Decision Ordering Supplemental Mid-Term Reliability Procurement, 02/28/2023
- Decision Fact Sheet, 03/14/2023
- Proposed Decision Ordering Supplemental Mid-Term Reliability Procurement, 01/13/23
- Decision Fact Sheet, 02/06/23
- D.21-06-035: Final Decision Requiring Procurement to Address Mid-Term Reliability, 6/24/2021
- Press Release, 6/24/2021
- Fact Sheet, 7/01/2021
- Proposed Decisions Requiring Procurement to Address Mid-Term Reliability
- Administrative Law Judge's Proposed Decision, 5/21/2021
- Commissioner Rechtschaffen's Alternate Proposed Decision, 5/21/2021
- Press Release, 5/21/2021
- Fact Sheet, 5/26/2021
- Administrative Law Judge's Ruling Seeking Feedback on Mid-Term Analysis and Proposed Procurement Requirements, 2/22/2021
- Fact Sheet , 2/24/2021
- Need Determination Model, 2/22/2021
- Workshop Announcement, 2/24/2021
- Workshop Slides, 3/12/2021
- Workshop recording, 3/12/2020
- D.20-12-044 Final Decision Establishing Process for Backstop Procurement Required by D.19-11-016, 12/17/2020