• Enhanced Oversight and Enforcement of PG&E

    On April 15, 2021, the California Public Utilities Commission (CPUC) placed Pacific Gas and Electric Company (PG&E) into the first step of the CPUC’s Enhanced Oversight and Enforcement Process. The CPUC’s action was based on PG&E’s failure to sufficiently prioritize clearing vegetation on its highest-risk power lines as part of its wildfire mitigation work in 2020. PG&E has been ordered to make corrective actions to ensure it improves its safety performance.

    The CPUC designed the Enhanced Oversight and Enforcement Process as a condition for approving PG&E’s plan for exiting bankruptcy in May 2020. The Enhanced Oversight and Enforcement Process provides a clear roadmap for how the CPUC closely monitors PG&E’s performance in delivering safe, reliable, affordable, clean energy. The process does not supplant existing CPUC regulatory or enforcement jurisdiction and does not limit the CPUC’s authority to pursue other enforcement actions.

    See CPUC Resolution M-4852 placing PG&E in Step 1 of the Enhanced Oversight and Enforcement Process.

    This page will be updated with PG&E’s progress reports and information on Stakeholder Workshops as they are scheduled.

    Stakeholder Workshops

    PG&E Corrective Action Plan Workshop

    • When: June 23, 2021, 1 – 4 p.m.
    • Where: Remote access via webcast or phone, as follows:
      • Live video broadcast with English or Spanish captions via webcast: www.adminmonitor.com/ca/cpuc
        • Participants who choose to participate via webcast only will have audio and video, but will not be able to make verbal comment. If you would like to make comments during the meeting, refer to the phone-in information below.
        • For captions, after clicking on the name of the workshop, click the green button below the video for captions. Then select captions by clicking on the white icon next to the word “live” at the bottom of the video.
        • It will also be recorded and archived for future viewing. 
      • Phone: 800-857-1917, passcode: 5180519
        • Participants will have audio (in English) and will be able to make comments or ask questions.
    • Media Advisory
    • Meeting Materials
      • Coming soon

     

    Related Documents

    June 4, 2021 Administrative Law Judge’s Ruling Providing Staff Recommendations for Comment

    PG&E’s Revised Corrective Action Plan: Full text of the Corrective Action Plan submitted by PG&E pursuant to the requirements of Resolution M-4852. This revised version was served by PG&E via email on May 7, 2021.

    April 15, 2021 Press Release: Announcing PG&E’s placement in Step 1 of the Enhanced Oversight and Enforcement Process

    Resolution M-4852: Placing PG&E into Step 1 of the Enhanced Oversight and Enforcement Process adopted in D.20-05-053.

    Resolution M-4852 Appendix A: Full text of the Enhanced Oversight and Enforcement Process.

    CPUC Decision 20-05-053: Approving PG&E’s exit from Bankruptcy and adopting the Enhanced Oversight and Enforcement Process (detailed in Appendix A).

     


Immigration Guide