Transportation Electrification Activities Pursuant to Senate Bill 350

SB 350, the Clean Energy and Pollution Reduction Act of 2015, established a 2030 greenhouse-gas reduction target, raised the state's renewable energy requirement to 50 percent, mandated a doubling of energy efficiency, and required the state to increase the efficiency of travel.  

SB 350 directs the CPUC to require California's six investor-owned electric utilities (IOUs), including PG&E, SCE, SDG&E, PacifiCorp, Bear Valley Electric Service, and Liberty Utilities, to file Applications for programs that “accelerate transportation electrification.” The goal of these programs is to reduce petroleum dependence, increase zero-emission vehicle adoption, improve air quality, and cut greenhouse gas emissions, in support of the state’s broader 2030 climate targets under SB 350.

Learn more about the CPUC's implementation of SB 350 here

This webpage documents the CPUC's implementation of transportation electrification activities pursuant to SB 350:

  • Overview of key CPUC Decisions authorizing IOU SB 350 pilots and programs
  • Third-party evaluations of program performance
  • Current reporting requirements, established by D.25-12-005
  • Legacy reporting requirements
  • Safety compliance checklists
  • 2019 Data Collection Workshop
  • Other Past Workshops and Events

Decisions Approving Pilots & Programs

An overview of CPUC Decisions authorizing IOU programs pursuant to SB 350 is provided below:

D.22-12-054, PG&E EV Charge 2 program

  • Authorized PG&E’s light-duty EV Charge 2 program to spend up to $52.2 million to implement its EV Charge 2 program to install Level 2 and DCFC ports at apartments, workplaces, and public destination sites. In D.23-09-005, the CPUC granted a Petition for Modification which allowed PG&E not to implement Phase 1 of the program.

Read Decision (PDF)                                

Read Petition for Modification (PDF)

 

D.21-11-014, SDG&E Power Your Drive Extension program

  • Authorized SDG&E to spend up to $43.5 million to build Level 2 chargers at apartments, sites serving apartment dwellers, and workplaces.  

Read Decision (PDF)                

 

D.20-08-045, SCE Charge Ready 2 program

  • Authorized SCE to spend up to $436 million on a second phase of its Charge Ready program, installing Level 2 chargers at apartments, workplaces, and destination centers, DCFC in public locations, and Level 2 chargers at new construction apartments.

Read Decision (PDF)                

 

D.19-08-026, SDG&E Power Your Drive for Fleets program

  • Approved a Settlement Agreement authorizing SDG&E’s Power Your Drive for Fleets program to spend up to $107 million to support make-ready infrastructure for medium- and heavy-duty EV charging.

Read decision (PDF)                 

 

D.18-09-034, Small IOU SB 350 programs

  • Authorized $7.33 million for PacifiCorp, Bear Valley Electric Service, and Liberty Utilities to fund eight transportation electrification programs and pilot a new EV rate, with $301,999 set aside for evaluation alongside the larger utilities' programs.

Read decision (PDF)

D.18-05-040, SB 350 Standard Review Projects

  • The Commission's largest SB 350 investment; authorized $738 million for medium- and heavy-duty make-ready EV charging programs in PG&E and SCE territory, PG&E’s EV Fast Charge DCFC make-ready program, and a residential charging rebate program for SDG&E customers.

Read decision (PDF)   

 

D.18-01-024, Priority Review Projects

  • CPUC’s first SB 350 approval, authorizing $42 million for 15 "priority review" pilot projects from the three large IOUs, which were fast-tracked through an expedited schedule.

Read decision (PDF)                 Press release

Standard Review Program (SRP) Evaluations- Medium and Heavy-Duty (MDHD) and Schools and Parks Programs

CPUC Decisions authorizing the IOUs’ MDHD programs also established funding for third-party evaluation of the programs. Programs have been evaluated annually since 2021. Additionally, programs serving schools, state parks and beaches authorized under AB 1082/ AB 1083 are also included in the annual evaluation. The evaluation measures whether SB 350-funded programs delivered on the state's adoption, air-quality, and emissions goals, assesses whether programs maximize benefits and minimize costs, and analyzes charger utilization, EV adoption, cost, emissions reduction, and grid impact data.

Year 5 Report (Evaluation Year 2025) 

  • Report
  • Presentation of Public Presentation webinar will be available in Oct 2026.

Year 4 Report (Evaluation Year 2024)

Year 3 Report (Evaluation Year 2023)

 Year 2 Report (Evaluation Year 2022)

Year 1 Report (Evaluation Year 2021)

Standard Review Program Evaluations - Light Duty (LD) Programs

The IOUs’ LD programs have been assessed through annual evaluations focused on each program.

SCE Charge Ready Light Duty Program

Final Evaluation Report (California Investor-owned Utility Transportation Electrification Priority Review Projects)

All six IOUs in the state implemented Priority Review Programs of Final Evaluation Reports. While PRPs piloted diverse approaches to accelerating TE, they encompassed three main project categories: fleet electrification, public access stations, and electrification education and awareness. These IOU pilots were all evaluated in one final report.

Current Reporting Requirements (D.25-12-005)

As of December 2025, D.25-12-005 consolidated CPUC TE data reporting, including for currently active SB 350 programs into a single, annual report.  To access the Annual TE Programs and Initiatives Compliance Report template, please visit our Reporting page: Resources and Reporting.

Legacy SB 350 Reporting Templates

Before D.25-12-005 consolidated TE data reporting, many SB 350 programs had dedicated templates; D.18-01-024, D.18-05-040, D.18-09-034, and D.20-08-045 establish utility data collection and reporting requirements for their respective TE programs. While no longer in effect for future reporting, past templates are provided for reference.

SCE Charge Ready 2

Standard Review programs Data Template

Priority Review Programs

Safety Requirements Checklist & Compliance Reporting

The Safety and Enforcement Division worked with the Energy Division to develop safety checklists to protect utility workers, contractors, and program participants during installation.  IOUs must file reports demonstrating compliance.

Workshop in May, 2019 - Data Collection and Reporting Efforts

In 2019, Energy Division staff held a workshop (agenda is here) to finalize data collection and reporting templates for priority review programs, and develop methodologies for broader IOU TE program evaluation going forward. Workshop presentations and comments from parties are available below:

PRESENTATIONS

  1. CPUC: Metrics and Methodologies for Evaluating TE Programs - Carrie Sisto
  2. Energetics: SB 350 TE Program Process / IOU and Evaluator Perspective - Ziga Ivanic
  3. CARB: Emissions Modeling, ZEV Programs, & Data Collection - Joshua Cunningham and Yachun Chow
  4. CEC: Benchmarking the Costs of Infrastructure and Services - Noel Crisostomo
  5. Cadmus: Evaluation Methodologies from Other Practice Areas - Philip Kreycik
  6. EPRI: 2019 Electric Transportation - Dan Bowermaster
  7. UC Davis Policy Institute for Energy, Environment and the Economy: Evaluation Processes for Energy Programs - Austin Brown
  8. UC Davis PH&EV Center: Data Collection and Evaluation - Gil Tal

COMMENTS

  1. The Alliance for Transportation Electrification
  2. Joint Comments from East Yard Communities for Environmental Justice, Center for Community Action and Environmental Justice, Sierra Club, and Union of Concerned Scientists
  3. The Utility Consumers' Action Network (UCAN)
  4. The Utility Reform Network (TURN)
  5. California Public Advocates Office
  6. Joint Comments from the Natural Resources Defense Council, the Coalition of California Utility Employees, Greenlots, Siemens, eMotorWerks, EVBox Inc., the Alliance of Automobile Manufacturers, Environmental Defense Fund, and Plug-In America
  7. San Diego Airport Parking
  8. Southern California Edison
  9. Pacific Gas and Electric
  10. Green Power Institute

Other Past Workshops and Events

February 27, 2018: Energy Division staff workshop on SB 350 transportation electrification reporting templates pursuant to D8-01-024.

  1. Agenda

December 4, 2017, 6 p.m.: Community meeting in Fresno to get input from the public on the transportation electrification plans of PG&E.

  1.  Read More
  2. View the CPUC's Presentation from the Meeting

September 2017: The CPUC held three community meetings to get input from the public on the transportation electrification plans of SDG&E, Southern California Edison, and PG&E.

  1.  Read more
  2.  View the CPUC’s Presentation from the Workshops

August 31, 2017: Pre-Hearing Conference on the transportation electrification applications of Bear Valley Electric, PacifiCorp, and Liberty Utilities

  1. Agenda

July 11, 2017: CPUC Workshop on the standard review projects in PG&E, SCE and SDG&E's Transportation Electrification applications

  1. Agenda
  2. Presentation
  3. Energy Division Staff Summary of the standard review proposals
  4. Recording of the WebEx

May 17, 2017: CPUC Workshop on on the priority review projects in PG&E, SCE and SDG&E's Transportation Electrification applications

  1. Agenda
  2. Presentation
  3. Recording  
  4. Energy Division staff Discussion Document 

February 8, 2017: CPUC workshop for PG&E, SCE, and SDG&E to each provide an overview of their transportation electrification applications:

April 29, 2016: CPUC workshop on the transportation electrification requirements established under SB 350.

  1. Agenda  
  2. Workshop recording
  3. Presentations: